Countdown to launch
T-minus 12 weeks to go.
The technical switch from our current systems to Workday will be incredibly intricate. It will require all of us to follow key milestones in the weeks and days leading up to the initial go-live on 8 February 2027.
As more details about this 'cutover' phase are confirmed, we'll keep updating this page with any end dates, freeze periods, start dates, required actions and question responses related to common processes.
Cutover explained in more detail
Transformations of this scale require organisations to work through a structured sequence of actions to make sure every aspect of the launch goes ahead safely and smoothly: freezing all activity in our current systems (like Agresso and ResourceLink), switching over our system integrations to fully test security and reporting, and migrating and verifying all the data before the initial launch day.
For most processes, this freeze will take place from 15 January to 8 February, but some processes need a longer pause in the lead-up. This balance gives the programme team enough time to work through everything, while letting us all continue working as normal for as long as possible. This might be inconvenient or uncomfortable for some of us, but cutover makes it possible to keep payroll and other crucial operations running without interruption.
Confirmed pre-launch deadlines
You can also track these dates by following a live Google Calendar.
| Date | Overview |
|---|---|
| 30 October 2026 | Deadline for submitting requests for new suppliers |
| 27 November 2026 | Deadline for raising new purchase orders for goods or services |
| 30 November 2026 | Deadline for requesting cash advances for travel |
| 8 December 2026 | Deadline for PIs to notify Pre-Award teams of grants for approval |
| 15 December 2026 | Deadline for requesting new grant funders for setup |
| 18 December 2026 | Deadline for coding and approving purchase card transactions |
| 18 December 2026 | Deadline for completing reconciliations for cash advances |
| 18 December 2026 | Deadline for setting up new customers in Agresso |
| 18 December 2026 | Deadline to submit data for Semester 2 Graduate Teaching Assistants |
| 22 December 2026 | Deadline for initiating customer (sales) credit notes |
| 4 January 2027 | Deadline for Graduate Teaching Assistants to formally accept their offers |
| 5 January 2027 | Deadline for approving customer (sales) credit notes |
| 6 January 2027 | Deadline for goods receipting call-off orders |
| 6 January 2027 | Deadline for reviewing and saving details of active call-off orders |
| 6 January 2027 | Deadline for submitting invoices for purchase orders |
| 6 January 2027 | Deadline for submitting staff, student or visitor expense claims |
| 6 January 2027 | Deadline for submitting approved student-related payment requests |
| 6 January 2027 | Deadline for submitting studentships or other student payments |
| 6 January 2027 | Deadline for PIs to provide grant details to Pre-Award budget teams |
| 8 January 2027 | Deadline for actioning out-of-tolerance tasks |
| 8 January 2027 | Deadline for approving all pending expense claims |
| 8 January 2027 | Deadline for goods receipting standard (non-call-off) purchase orders |
| 8 January 2027 | Deadline for initiating customer (sales) invoices |
| 8 January 2027 | Deadline for submitting non-purchase-order or research invoices |
| 11 January 2027 | Deadline for submitting Alma library service requests |
| 11 January 2027 | Final payment run is carried out in Agresso |
| 12 January 2027 | Deadline for approving customer (sales) invoices |
| 14 January 2027 | Worktribe becomes unavailable for all staff |
| 15 January 2027 | All activity freezes in Agresso and ResourceLink |
| 15 January 2027 | Deadline for posting customer receipts to Agresso |
| 8 February 2027 | Workday launches |
Confirmed guidance on key topics
New suppliers
Why we need to pause new suppliers
Freezing requests for new suppliers from the end of October collectively gives us enough time to: undertake due diligence; perform risk and impact assessments; approve the supplier; raise requisitions; approve purchase orders; receive the goods or services; receipt into Agresso and YEP; approve the invoice; and pay the invoice. This process applies to each and every new request, so a later freeze date would seriously complicate and compromise our ability to manage that aspect of the transition.
While it’s possible to transfer open, unreceipted orders from Agresso and YEP into Workday, this comes with considerable downsides, the main being that you would lose your access to those orders. In practice, a team would have to manually send out receipting requests for those Agresso and YEP orders, as this cannot be mechanised. As such, we need to avoid this wherever possible.
Solutions and considerations
In almost all cases, it should be possible for all of us to avoid the need to create new suppliers throughout this three-month freeze. We suggest using one of the following options:
- Use an existing supplier: Unless your requirements are especially niche, an existing supplier is likely to provide them. As a first step, if unsure, you can post to the #yep-users Slack channel with an overview of the goods or services you need, and someone will respond with recommended active vendors.
- Purchase using a GPC card: If you’ve been issued a GPC card, and need a temporary limit increase to pay a new supplier within this window, you can contact pcard@york.ac.uk to request it. Any organisation should be able to accept card payments; usually, any pushback relates to reservations around the minimal service charge, and not an inability to do so. University policy makes clear that no one should verbally instruct third parties to deliver goods or perform services outside the financial regulations; the process should start with the paperwork to avoid unforseen invoices that cannot accept card payments.
- Delay the purchase: We recognise this won’t be ideal, but please consider if the activity related to a new supplier can hold off until after the Workday go-live. If so, we recommend referring to the existing supplier setup guidance to begin your discussions and due-diligence activity with your new supplier in the background now, to then submit your request mid-February for approval.
Exceptional circumstances
You may be in a situation in which all of the following apply:
- No existing supplier is available who can meet the need (acknowledging that they might not be the best)
- The service or goods are business critical (ie, critical and time-sensitive work of the University is at risk without the new supplier)
- The supply, or payment for the supply, cannot be delayed such that we can create the new supplier after go-live
- The supplier will not accept payment with a GPC Card
If so, please seek endorsement from your DFO or Director of PS that your request is business critical, and ask them to forward your request to finance-director@york.ac.uk using the subject 'Business critical emergency new suppliers', briefly outlining why all of the above apply. In these highly exceptional circumstances, Finance will consider issuing a written letter of commitment in lieu of a purchase order. They can only do this for a small number of highly exceptional purchases, due to the labour-intensive nature of the process.
Inactive suppliers
The Finance team has paused the automatic closure of inactive supplier subscriptions for the transition. Under normal circumstances, suppliers only close if they have been dormant (without any activity) for 18 months, so the risk of them being removed in this window should therefore not apply.
School partnerships
For new partnerships, like schools, the partnership agreement acts as our formal commitment to them. Invoices for new schools onboarded for Semester 2 typically arrive in late February or early March, at which time Workday will be live for submitting new-supplier requests.
Purchase orders
The freeze rationale
When we transition to Workday, any migrated purchase orders (POs) will no longer be directly accessible in the system by the original raiser. Instead, when an invoice arrives, Finance will have to manually assign goods-receipt tasks to order owners.
With over 6,000 open orders currently in Agresso, migrating open POs creates significant processing delays and heavy manual workload for everyone involved. To ensure suppliers are paid on time, and to avoid processing delays after go-live, we must close out as many Agresso orders as possible.
Key deadlines
The final day to place orders in Agresso for any goods or services expected to be delivered before the end of December is 27 November. Access to raise new purchase orders in Agresso will be switched off after this date.
If you miss this deadline, you’ll have to raise the order in Workday after go-live. If an urgent need arises after the deadline, please explore if it can be paid for by University purchase card.
All goods reciepting needs to be completed by 8 January. Orders that are not fully approved and goods receipted by the specified deadlines will not be processed in the final Agresso payment run. This will result in delayed supplier payments and additional administrative steps to resolve unpaid invoices post-go-live.
Actions for staff groups
If you're an order raiser or requisitioner:
- Goods receipt immediately on receipt: Goods receipt any completed orders in Agresso as soon as goods or services are delivered.
- Direct invoices to Accounts Payable: If a supplier sends an invoice directly to you, forward it to Accounts Payable immediately.
- Pause non-urgent orders: If goods or services will not be delivered before the end of December, do not raise a PO in Agresso. Wait to raise it on Workday after go-live, or use a University purchase card for urgent items.
- Notify approvers: For essential new orders over £150 placed before 27 November, alert your approver in advance to ensure rapid approval.
If you're an order approver or manager, review and approve all pending requisitions promptly to enable goods receipting by 8 January.
Urgent orders
If you have an urgent order that cannot follow the timeline above, mitigations are available only if all of the following criteria are met:
- The purchase is business-critical (unavailability poses a severe risk to time-sensitive University operations).
- The order or payment cannot be delayed until Workday go-live.
- The supplier cannot accept payment via University purchase card.
If you're in this situation, obtain written endorsement from your Director of Faculty Operations or Director of Professional Service. Request that they forward your justification to finance-director@york.ac.uk with the subject line: 'Business critical emergency orders'. In exceptional cases, Finance may issue a formal letter of commitment.
Because this is a highly manual process, it is strictly reserved for critical emergencies.
Supplier communications
Finance has contacted over 700 key suppliers (those who receive £50k or more from us annually, those who receive two or more purchase requests a month, and all catalogue suppliers) to inform them of the transition, advise on interventions and mitigations, and respond to their queries directly.
Call-off orders
Retaining order ownership
We are updating how call-off purchase orders (long-term blanket orders with multiple recurring invoices) are managed as we transition from Agresso to Workday from 8 February 2027.
To ensure you retain full ownership and control over your budget and order approvals in Workday, routine departmental call-off orders will not be automatically migrated from Agresso.
If routine orders were migrated automatically, order ownership in Workday would transfer to central system administrators; this would require Finance to manually delegate every future goods-receipt task back to you, causing severe invoice payment delays.
Closing legacy call-offs and recreating them in Workday ensures you retain direct ownership, approval visibility and payment history for your orders.
Key actions and timeline
Before 6 January 2027: review and save call-off orders
- Log into Agresso and review all your active call-off orders (eg, recurring catering, annual lab consumables, monthly utility/office supplies).
- Save or print a PDF copy of each active call-off order. You will need the remaining unbilled line items, supplier details and Cost Centre coding to later re-raise the order in Workday.
- All call-off orders will be closed by Procurement after the final payment run, which is on 11 January.
Pre-cutover freeze: clear pending invoices and goods receipt
- Ensure your suppliers submit all outstanding invoices for goods/services by 6 January 2027 so they can be matched and paid against your current Agresso PO.
- Ensure that you goods receipt and action all out-of-tolerance tasks by 6 January 2027.
After go-live: recreate call-offs in Workday
- Log into Workday and raise a new call-off order for the remaining period of the financial year (eg, February to July 2027). Only enter the remaining unbilled value (not the original full-year contract value).
- Add a note in the supplier field stating: ’Continuation of closed Agresso PO [insert old PO number] – Do not duplicate delivery. And please quote this new order number on all future invoices’.
Role-specific responsibilities
- Requisitioners: Save legacy call-off details now and re-raise open-balance POs in Workday after 8 February.
- Line managers and budget holders: Review and approve any outstanding approval tasks in Agresso.
Step-by-step Quick Reference Guides and short video walkthroughs showing how to set up call-off orders in Workday will be shared nearer go-live
Supplier communications
Finance has contacted over 700 key suppliers (those who receive £50k or more from us annually, those who receive two or more purchase requests a month, and all catalogue suppliers) to inform them of the transition, advise on interventions and mitigations, and respond to their queries directly.
Faculty stores
External purchases
You will be unable to raise purchase orders after 27 November, so it’s key that you plan ahead to purchase any goods or raise POs for services you may need to cover activities until the end of February. The ‘go-live’ date for Workday is 8 February, but the delivery time and any possible delays should be considered.
Stock
Faculty Supply (Stores) will buy in the anticipated stock required to cover sales during this period, utilising additional storage space. To give the maximum space available to do this, please stock up your individual labs with the consumables you’ll need from us as much as possible before w/c 23 November. This will allow us to restock Stores before the freeze to give us the maximum stock.
You will be able to continue to order from Faculty Supply (Stores) via the barcode cards until early January, and from then until Workday is live we’ll make a record of your purchases against your workorder or Cost Centre, which we’ll then manually add in Workday (with guidance to follow). You will always be able to order stock from Faculty Supply (Stores) during this whole process.
Dry ice, liquid nitrogen and waste
These services run on annual blanket purchase orders, and will be unaffected by the purchasing freeze. If you require additional dry ice, please contact either biol-stores@york.ac.uk or chem-stores@york.ac.uk as appropriate, and we will order it for you on our PO and cross-cost after the fact.
Gas cylinders and solvents
We cannot hold enough gas cylinders to cover this freeze period due to storage limitations. We have a plan to be able to continue to order gas cylinders. If you need to order gas directly from BOC (ie, not purchased through Stores), please raise purchase orders to cover the number and deliveries you’ll need. You can then draw down from this PO as needed. Eg, if you need one cylinder a month, raise a PO to BOC Gases for the cylinder, quantity x3 and a separate line for x3 delivery charge.
When you need a cylinder to be ordered, email biol-purchasing@york.ac.uk or chem-stores@york.ac.uk as usual, telling us how many are to be ordered and we’ll do that for you. It may be worth adding an additional quantity in case and if it’s not used, the order will be closed later. We have capacity to hold more solvents than usual and have a plan to ensure supply too.
Credit cards
Part of the University contingency plan is for purchases to be made via credit card. Existing purchase credit cards will have their limits increased (the distinction between travel and purchase cards remains, so do not use a travel card to purchase goods). Please use the usual method of credit card orders for your department.
There may be an additional delay in processing these due to increased volume. If you know you’re likely to need this, please check in advance if your supplier accepts credit card payment.
Oligos, primers and sequencing
As you won’t be able to use the Oligo module, you can look into pre-paid accounts, such as MPower cards from Merck/Sigma or OligoCard from IDT. You can contact the relevant Reps for help on how to set these up. Remember to stock up on any prepaid sequencing barcodes you may need.
Shipping
This can continue as usual. We’re sorting out for these invoices to be paid by credit card during the freeze. Biology won’t be able to raise a PO for shipping costs, so please ensure you enter a valid workorder on the Courier Booking Form for the cost to be charged to. As this process will take longer than usual, please be sure not to use a workorder nearing expiry.
Support
Stores are expecting a significant increase in deliveries in November and early December as you get your external orders delivered. As a result, there may be times when processing your orders takes longer than usual, the counter may need to close at peak times, and there may be delays in answering emails and queries. Your patience is most appreciated, and we’ll let you know via email as much as possible. If you are emailed to collect goods, please do so promptly.
Thank you for your understanding as we provide you with support in Teaching and Research activities. If you have any questions, please email your relevant teams (biol-stores@york.ac.uk, chem-stores@york.ac.uk or PET-stores@york.ac.uk) and we will try to answer or direct them to someone who can.
Purchase cards
Key actions before 18 December
As part of the transformation, we are transitioning from Barclaycard Spend Management (BSM) to Workday for corporate card coding, receipt submission and transaction approvals. To ensure a smooth transition and prevent duplicate transaction processing, we will enforce a strict cutover period prior to our Workday go-live on 8 February.
Access to BSM will be permanently removed for all users after 18 December. All coding and approvals must be fully completed by this date.
- Cardholders: Log into BSM and code all your outstanding transactions, ensuring all receipts are available.
- Approvers and line managers: Review and clear your entire BSM approval queue before the cutoff date.
Unapproved transactions
Any transactions that are not coded or approved by 18 December will automatically be coded to your department's default workorder, and forwarded to Rachel Devaney (Director of Procurement and Transactional Services) for central review and approval. Such centralised cost apportionment means that costs will not be charged to the correct workorder or project, and these will require re-coding in Workday post go-live by you working with your management accountant.
We strongly urge all cardholders and approvers to clear their queues now to avoid creating this avoidable administrative burden for your department during a busy transition period. Maintaining up-to-date transaction coding and approvals is a core requirement of holding a corporate card, and so cardholders who fail to clear outstanding admin by 18 December risk having their card privileges suspended.
Guidance for the blackout period
- Card usage: You may continue using your purchase card as normal during this period (19 December to 7 February).
- Receipt capture: Keep all physical and digital VAT receipts for purchases made during the blackout period. You will need to upload these into Workday against your purchase card transactions once Workday goes live on 8 February.
- No access to BSM: You will not be able to view, code or approve transactions until Workday goes live.
- Card limits and pre-planning: Card-limit increases remain available for genuine needs, but requests made ‘just in case’ will not be approved. Please plan your purchasing requirements immediately, and place orders via existing YEP/Agresso suppliers now to ensure delivery and payment before cutover deadlines.
After go-live
From 8 February onwards, all purchase card management will take place directly within Workday (via desktop or the Workday mobile app). This includes viewing, coding and approving transactions, and uploading receipts. Further guidance will be shared across the coming weeks as part of the wider functional support and training rollout.
If you have any questions regarding this transition or your purchase card account, please contact the Procurement team at pcard@york.ac.uk.
Workorders
Pausing workorder creation
In Workday, we'll have a different structure and level of granularity for our chart of accounts, replacing our current use of workorders.
As of October, the Finance team have removed most Agresso users' access to be able to create and amend core workorders in this interim period before Workday goes live in February. In this time, workorders can still be closed and amended (changing names, recipients, etc). Spend should be booked to a workorder in the relevant department that already exists.
A limited number of people have retained access to create workorders for externally funded projects (such as research, endowments and externally funded studentships).
If you have any questions on specific grants, you can contact finance-accounts@york.ac.uk. All queries relating to research projects should go to research-grants@york.ac.uk.
Customers
Key deadlines at a glance
We are beginning to close out external customer invoicing activities in Agresso. To ensure a smooth transition and prevent duplicate transaction processing, we will enforce a strict cutover period prior to our Workday go-live on 8 February.
- 18 December 2026: Final day for setting up new customers in Agresso. After this date, any new customers will need to be set up in Workday after go-live.
- 22 December 2026: Final date for initiation of sales credit notes.
- 5 January 2027: Final date for approval of sales credit notes. No sales credit notes will be processed and sent to customers after this date.
- 8 January 2027: Final date for initiation of sales invoices.
- 12 January 2027: Final day for approval of sales invoices. No sales invoices will be processed and sent to customers after this date.
- 15 January 2027: Final day for posting customer receipts to Agresso.
Any sales invoices that have not been fully approved by the deadline will need to be raised in Workday after go-live (8 February). This may result in delayed payments being received from customers, so please try to plan ahead.
Actions required by role
For colleagues who set up new customers and raise sales invoices:
- Identify urgent sales invoices: Identify key goods and services that need to be billed to customers prior to 8 January, initiate these sales invoices and, where relevant, let approvers know these will need approval.
- Pause non-urgent sales invoices: If goods or services will not be delivered to the customer (or if you know that we will not get paid) until after 15 January, do not raise a sales invoice in Agresso. Wait until after go-live to raise the sales (customer) invoice in Workday.
- Issuing sales credit notes: If you are aware that a customer has been charged incorrectly for services, then you need to generate a credit note to that customer in Agresso by the deadline date above. Please speak to the Fees team if you are unsure about how to do this.
- Notify approvers: Alert your approver in advance that you will be raising sales invoices to ensure that these get approved quickly where required by the deadline date.
For sales invoice approvers:
- Prioritise Agresso approvals: Review and approve all pending sales invoice and credit-note requests by close of play on 12 January 2027.
After go-live
From 8 February onwards, all customer activities will take place directly within Workday. The customer set-up and invoicing process in Workday works in a similar way to Agresso. Setting up new customers will be initiated by colleagues in Workday, and this is workflowed to the Fees team to undertake relevant checks prior to making the new customer active.
Similarly, sales (customer) invoices are initiated in Workday and workflowed for approval prior to being sent to the customer automatically. Guidance on these processes will be provided closer to the Workday launch.
Expense claims
Deadlines for current expense claims
All current expense claims must be fully submitted to Accounts Payable by Wednesday 6 January (to be paid on 15 January). If your departmental administrative team currently processes expenses on your behalf, your local submission deadline may be earlier than 6 January to allow time for processing; if so, your local admin teams will advise you of these deadlines.
If you are an approver of expenses, you will need to clear all pending expenses by Friday 8 January.
Blackout window (7 January to 7 February)
Due to the cutover, any expense processing will be frozen during this period. You should keep all itemised expense receipts incurred during this time to submit your expense claim via Workday after 8 February. We're planning a brief, phased rollout of access to the expense process in Workday after this initial go-live date.
Please plan ahead, and remember that you can minimise expense claims by booking your travel via the University’s contracted Travel Management Companies and using a purchase card for other permitted expenses.
Keep in mind University policy that states that you cannot claim for an expense that you incurred over three months before submission. You will therefore not be able to submit a claim in Workday that has a receipt date of early November 2026, for example, and will therefore not be reimbursed.
Claiming expenses after go-live
Currently, administrative practices for claiming expenses vary widely across the University. In many academic departments, local Professional Services staff submit expense claims on behalf of academic colleagues. As part of moving to a single system, Workday will give us one simple, efficient way to manage expense claims in the future.
After go-live, expense claims will be treated as a personal declaration. This means that staff will be expected to submit (and upload receipts for) their own expense claims directly in Workday, and take responsibility for complying with relevant policies, which have been configured into the Workday submission steps for ease. Local administrative staff will no longer be able to raise routine expense claims on your behalf.
Workday makes direct access fast and intuitive, meaning that you will be able to create and submit your own expenses quickly and easily in real time. This includes using the Workday mobile app to take photos of paper receipts on your phone, and upload them into Workday in seconds. You will also be able to track the status of your claim as it progresses through the process.
Next steps and support
This is a significant cultural shift for departments accustomed to admin-assisted expense submission. Although this might be different from the way you currently submit your expenses, the increased automation and streamlining of the process will significantly reduce the time it takes for reimbursement for routine claims.
Training, guidance and video demonstrations showing how to quickly submit expense claims will be rolled out in December and January before the initial Workday go-live in February.
Non-staff expenses
6 January is also the deadline for non-staff expense submissions (students, guest lecturers, visiting academics, research participants and others), which will be paid on Friday 15 January. Admin Managers have been provided with template guidance to request early submission of expense forms, itemised receipts and bank details to allow time for processing within departments.
All expense processing will pause during the freeze window (7 January to 7 February) while we switch systems. As such, non-staff are also advised to retain all itemised receipts during this period to then submit them for reimbursement after 8 February. When Workday is live, the submission process for non-staff expenses will remain largely unchanged from the current process.
Student payments
Key dates and actions
- 6 January 2027 (5pm): Final deadline for all student-related payment requests to be fully approved and submitted to Accounts Payable for entry into Agresso.
- 11 January 2027: Final Agresso payment processing run before cutover freeze (actual payment date is Friday 15 January).
Payment requests up to and including 6 January must include all payments due to students between 11 January and 19 February. As a result, some students due a payment during the freeze window will receive their funds earlier than usual.
Any student payments not fully approved and submitted to Accounts Payable by 6 January will miss the final Agresso payment run. Unprocessed items will be frozen until after Workday goes live in February, which will result in payment delays and require manual re-processing post-launch.
Setting early local deadlines
Because final payment records must be approved and in Agresso by 6 January, departmental admin teams will need sufficient lead time beforehand to collate, approve and submit student payments; they have been advised to establish and communicate early local deadlines to impacted department budget holders, supervisors, researchers, students and anyone else who needs to be aware, particularly given the University’s winter closure period.
Actions for supervisors and budget holders
If you manage or authorise studentship payments, stipends or student prizes due to be paid between 11 January and 19 February, you must submit all approved requests and supporting paperwork in line with these dates and guidelines. Please check your upcoming awards and stipend schedules now, and ensure any new student bank details or authorisation forms are submitted promptly.
Cash advances
Reconciling outstanding advances
Due to technical differences in how Workday processes financial records, existing cash advances cannot be migrated from Agresso to Workday. To ensure our accounts are fully balanced and clean prior to system switchover, every single outstanding travel cash advance issued in Agresso must be fully reconciled before the system closes.
Because the reconciliation process requires multiple steps – claimants returning from travel, receipt submission, departmental approval and final Finance processing – combined with the upcoming Christmas closure, we must implement a strict cut-off schedule.
Because Agresso is being permanently closed, and data cannot be carried over, Finance will be unable to reconcile any outstanding advances after 18 December. If an advance remains unreconciled by this date, the University will be legally and operationally required to issue an invoice to the individual to recover the advance in full. Therefore, we strongly encourage completing reconciliations as early as possible to prevent this issue.
Interim solutions
To ensure business continuity while advances are paused, please use the following alternative channels:
- Travel Management Companies (TMCs): Book flights, trains and accommodation directly through our approved travel partners so expenses are billed directly to the department.
- Departmental Purchasing Cards (P-Cards): Use departmental credit cards for upfront travel costs where possible.
- Out-of-pocket expense claims: Staff may pay expenses directly and submit standard expense claims, which will be processed in line with published cut-off dates.
Travel bookings
Updating department structures
We are building a direct integration between our contracted travel suppliers' systems (Selective Travel and Clarity Travel) and Workday to automate how we receive, process and pay invoices.
Part of the transformation involves making some changes to align with our new chart of accounts. In preparation, we've done some housekeeping of the department structure on the Selective system: removing some departments that no longer exist, and aligning others to 'parent' departments. You should still use your usual workorder(s) when making your booking.
For those departments where we are realigning to parent departments in the travel system, any affected user profiles have also been moved to the parent department automatically, which will be reflected on the Selective checkout page.
We are not changing the front-end online booking tools. They will not be accessed via the new Workday system, so you will still access the booking tools in exactly the same way that you do now via the Selective Hub or ClarityGo portal.
If you have any questions about the changes to Selective Travel or Clarity Travel, you can reach out to Donna Lyon (donna.lyon@york.ac.uk) directly.
Grant applications
Context and key dates
To migrate data from our current systems into Workday, Worktribe will enter a freeze period from 4pm on Thursday 14 January 2027 until Workday go-live on Monday 8 February 2027. During this freeze, Worktribe will be unavailable to all staff, including Pre-award Teams, and so standard costing, approvals and the associated funder submissions will be paused.
The Project Team is working on a solution that may enable limited, at-risk access to Worktribe for Faculty Research Operations (FRO) colleagues and approvers to perform critical actions, but this will only be for 2-3 days each week of the freeze period.
To manage capacity around the freeze, and the University winter closure, Pre-Award teams will prioritise grant applications with fixed external-funder deadlines up to Friday 19 February 2027.
Actions for Principal Investigators
To guarantee processing and approval ahead of the 14 January freeze, Principal Investigators (PIs) must meet the following deadlines:
- Tuesday 8 December 2026: PIs must notify their Pre-Award team in writing (via faculty-specific channels) with key project details (funding call, role, estimated budget, external partners).
- Tuesday 15 December 2026: Final deadline to request new funders to be set up in our system (ahead of Finance’s customer-creation cutoff on 18 December).
- Wednesday 6 January 2027: PIs must provide the following to Pre-Award teams: a finalised budget, an advanced draft of the application, and completed split and risk assessment tabs on Worktribe.
- Thursday 14 January 2027 (4pm): Worktribe begins its cutover freeze and closes to all staff.
- Monday 8 February 2027: Workday goes live and normal operations resume.
Other considerations
- Late requests: Any applications notified after 8 December cannot be guaranteed approval before the 14 January freeze; FROs will assess capacity on a case-by-case basis.
- Later deadlines: Responsive mode applications and grants with fixed deadlines after 19 February 2027 will continue to be supported alongside prioritised bids.
- Live grants (Post-Award): Separate guidance for PIs holding live grants will follow shortly regarding the transition of active project finances into Workday.
If you have any questions regarding departmental cutover planning, please contact your Faculty Research Operations team.
Casual workers
Casual worker arrangements
If you need to use casual workers between now and Workday go-live, the process will vary depending on the date(s) the work will take place. Please refer to the Casual workers cutover process (PDF
, 38kb) for this information. It is imperative that you follow the correct process to ensure a clean migration of data, and avoid unnecessary admin across departments and HR over the transition period.
Immediate actions
- For casual workers working between now and 10 January, please book them and approve time in Dashboard as normal.
- Do not register new casual workers on Dashboard if they aren’t starting work until after 10 January.
- Review the interim arrangements below (11 January to 14 February) and agree on local arrangements.
- By 23 December, Admin Managers (including IRPM), YCL managers and equivalents must complete this Google Form to nominate the relevant colleagues who will support the data-gathering exercise for migrating records from ResourceLink.
Timeline
- 4 January: Last week to start drawdown bookings in Dashboard.
- 6 January: Final deadline to submit retrospective bookings to HR Services.
- 8 January: Final date for new workers to register and complete a right-to-work check for Dashboard (only for those working 9 or 10 January).
- 10 January: Final deadline for workers to submit timesheets and amend personal or bank details in Dashboard.
- 11 January: Final deadline for managers or administrators to approve timesheets in Dashboard. Adopt the interim process prior to Workday go-live (details below).
- 21 to 29 January (provisional): Undertake data-gathering exercise to support record migration within Workday.
- 15 February (provisional): Workday functionality goes live for all colleagues to book, schedule and approve hours worked.
Casual work taking place from 11 January to 14 February
- No changes in Dashboard after 10 January: Any bookings, approvals, claims or record updates made after this date will be lost.
- Only offer work to current casual workers: Where possible, please limit work allocation to casuals who have been paid between 1 August 2026 and 10 January 2027. This will significantly reduce your post-go-live workload. In exceptional circumstances, if you must engage a new worker, we will provide a registration form for you to complete in advance of any work starting to allow time for right-to-work checks to be completed.
- Student visas: You must ensure any work offered to student visa holders does not exceed their maximum weekly hours permitted by UKVI.
- Record-keeping: Keep a record of all hours offered and worked between 11 January and 14 February. We have provided a model casual work tracker to capture all the data needed, but please feel free to amend to fit your local circumstances.
Migrating casual workers into Workday
Because our current payroll and HR systems lack the structured data needed to auto-create full Workday records, we will need your help gathering data to set up casuals who are due to work between now and 31 March 2027.
In January, we will send a list of casuals paid between 1 August 2026 and 10 January 2027 to the people nominated in the form above. They will need to select the relevant workers, and confirm the job profile and line manager so we can set them up in preparation of Workday going live.
All other workers must be hired into a position via the new Workday processes once the system goes live (guidance to follow).
Keeping casual workers informed
While we are sharing these updates through student newsletters and campus screens, please reinforce these key dates directly with your casual workers by signposting them to our dedicated web page.
Custom casual pay rates
As we prepare for our upcoming Workday launch, we are locking down our pay data for final system testing. Effective 20 November 2026, we have paused all requests for new custom casual pay rates.
- Existing casual rates (no change): All current casual pay rates remain active in Dashboard and available to use.
- New rate requests (closed): You will no longer be able to request brand-new custom casual rates while we complete the transition to Workday.
When hiring casual staff, please continue to select an existing rate in Dashboard.
- Use standard grade rates: Default casual rates should normally align with the bottom salary point of our framework grades, and all of these are already available in Dashboard (alongside pre-approved, role-specific rates).
- Match by rate, not job title: If the exact job title you want does not appear under the required pay point, select any existing option that matches the correct hourly rate for the role. This ensures the worker is paid accurately without delaying their setup.
If you are unsure which existing casual rate applies to a role, please contact rewards-team@york.ac.uk.
GTA staffing
Staffing requirements
We are preparing for the Graduate Teaching Assistant (GTA) staffing requirements for Semester 2. There will be shorter deadlines due to the unavailability of ResourceLink during the cutover period before Workday goes live in February.
The final deadline for departments to submit complete data for all new and returning GTAs is 18 December 2026, and the deadline for all GTAs to formally confirm and accept their offers is 4 January 2027.
Meeting these deadlines is essential to ensure HR can set up the payroll records during the short period that ResourceLink will be available in early January. Any submissions or acceptances received after these dates will miss the January payroll cycle, and will instead be processed through Workday in February.
Timetable and early submissions
Finalised timetables will be released to departments on 16 December 2026. However, if you have already identified the requirements for your new or continuing GTAs, please submit this information as normal at your earliest opportunity, and contact mandy.ward@york.ac.uk with any questions about these GTA Semester 2 arrangements.
I’ve managed this type of transition for over a dozen huge organisations. It’s always a tense and intense time – the culmination of everyone’s efforts – and most staff only see the tip of the iceberg of the preparation involved. We're working through various rehearsals as a whole team to familiarise ourselves with every date and detail, which will form the basis of the guidance we provide to all York staff throughout.
Peter Kettle, Cutover Manager