13th July 2009
POWER
- Problem in the York container with the main circuit, should be looked
at today.
INTERNET - Still problems with the satellite
system. We are in discussions as to alternative solutions
YorkLab - Everything off for now but until yesterday CO,
O3, MET, working well. GC-MS-problem with valves overheating and
mems flow.
Still some issues with
calibration of system. GC-FID-potential optic problem under
investigation. NOxy back to manufacturer for repair of peltier
cooling system.
IFT - Problem with compressor resolved.
MPI- All off until internet problems resolved.
1st June 2009
POWER - Finally breaker has been changed before York and
IFT leading to stable power and purposeful back-up generator!
INTERNET - Luis working on radio connection,
hopes to have it in operation this week.
YorkLab - CO instrument low sensitivity,
everything else (O3, MET, NOXY, GC-FID, GC-MS) working well.
SOS campaign running, FAGE having some
problems, PERCA running well, MAX-DOAS potentially a broken shutter,
GC-MS (Irvine) running well.
27th March 2009
POWER
INTERNET - VSAT system down, should be up
again early May. Radio connection being set-up.
York Lab - CO instrument low sensitivity
Ozone, Met fine
MS due to be on-line in early May
GC-FID running well
19th January
2009
POWER: Some problems with the back-up generator.
Cooler broken?
INTERNET- OK
York Lab - CO instrument broken, lamp problems
Ozone, GC, Met fine
NOxy running but
sensitivity still low, service due in mid-February
MS due to be
installed February
MAX-DOAS running ok
Spec Rad ok
IFT- Campaign in
progress
MAX-Planck ok
3rd November
2008
POWER: Stable (some problems during week-end)
Internet -
Ok
YorkLab - Compressor not
ok, part need to be replaced.
CO and Ozone and GC equipments OK.
Noxy running but NO sensitivity still low
MS in Bristol being repaired.
Max DOAS running ok
Hamburg SPEC
RAD ok
IFT - Equipments running OK.
Max-Planck -
Lab running ok
7th October 2008
POWER: Stable and Generator OK.
Still wait the licence for wind turbine instalation
Sending equipments- 20 ft container
sended to york since last week. Big box from IFT will be send during
the next days .
Internet - OK (satellite dish). Managing now
to get the wireless connection from the
institute.
YORK - CO,Noxy and Ozone equipments OK.
GC back to routine sequence
chromatograms looking much better now.
MS in Bristol being repaired.
Max DOAS running again.
IFT
- Equipments running OK .
MPI-Jena - Lena Kozlova
and thomas Seifert Back to Europe since yesterday.Lab is running.
18th September 2008
POWER: Stable and Generator OK
INTERNET: Internet working at the site but
further finance is needed to allow remote operation from outside.
YORK: CO, O3, NOxy running well
Major work has been carried out on the GC-FID
and is looking much better.
MS in Bristol being repaired
MAX-DOAS has been upgraded and is running
well.
IFT- Equipment running well.
MPI-Jena, Thomas and Reimer working on
greenhouse gas measurements. Calibration gases delivered this
week.
5th September 2008
POWER: Stable and Generator OK.
Sending equipments- 20 ft
container already available. waiting customs documents to be ready to
send the container.
INTERNET: Problems with internet
(satelite dish) seems to be solved. internet conection OK since two
days ago.
YORK - CO and Ozone equipments OK.
GC back to routine sequence but
chromatograms still not good.
Noxy running but Zero Air
generator has a problem.
MS in Bristol being
repaired.
Jens and Robert from Heidelberg
at the station.Max DOAS running again.
IFT -
Equipments running OK since the end of the last campain.
Max-Planck - Lena Kozlova and
Thomas at the station.2 more technicians arrived. Still waiting
for calibration standard cylinders stuck in sal, on the next ship.
21st August 2008
POWER: Stable during August and
Generator OK.
Sending equipments- 40 ft
container is back to the harbour.Preparing documents to send back
equipments in 20 ft container.
INTERNET: Satelite dish in
place but internet conections still with some
problems.
YORK:- CO and Ozone equipments
OK.
GC back to routine
sequence but chromatograms still not good.
Noxy running. Zero Air generator has
problems.
MS will be send back today to
Bristol to be repaired.
Heidelberg People will
arrive next week for Max DOAS reinstallation.
IFT - Equipments running OK since the end of
the last campaign.
Max-Planck - Lena Kozlova and
thomas arrived this morning the 22nd, and will stay until the
12th of
September.
20th August 2008
POWER: Back-up generator is
fixed,
power is stable.
INTERNET: Some problems with communication, hopefully
working in the next few days.
YORK LAB: CO, Ozone, and NOxy instruments running OK. Zero
Air generator has some problems.
GC-MS: Arranging to be shipped back.
GC-FID: Some contamination problems.
MAX-DOAS off
because
of mechanical problem with the equipment. Heidelberg people will
be here at the end of August to install new equipment.
Radiometer from
University of Hamburg OK.
Meteorological equipments
running OK.
Aerosol sampling from
U.of Southampton running with just one of the two pumps again.
Wind Turbine unloaded, container expected to be shipped
later this week.
11th August 2008
POWER: Back-up generator is being repaired today,
power has been stable for two weeks.
INTERNET: Satellite dish and internet will be installed
tomorrow.
YORK LAB: CO, Ozone, and NOxy instruments running OK.
GC-MS: Arranging to be shipped back.
GC-FID: Some contamination problems.
MAX-DOAS off
because
of mechanical problem with the equipment. Heidelberg people will
be here at the end of August to install new equipment.
Radiometer from
University of Hamburg OK.
Meteorological equipments
running OK.
Aerosol sampling from
U.of Southampton running with just one of the two pumps again.
31st July 2008
WIND TURBINE: Arrived. Waiting for planning permission
before we
can begin installation.
30th July 2008
POWER: Back-up
generator is still not working but a part will be replaced next
week. Power has been stable so far this week.
INTERNET:
Satellite dish has cleared customs and will be installed next week.
YORK LAB: CO,
Ozone, and Noxy instruments running OK.
GC running but still
has a some contamination problems.
GC-MS not
working. Preparing to send the MS back to Bristol to be fixed.
MAX-DOAS off because
of mechanical problem with the equipment. Heidelberg people will
be here at the end of August to install new equipment.
Radiometer from
University of Hamburg OK.
Meteorological equipments
running OK.
Aerosol sampling from
U.of Southampton running with just one of the two pumps again.Matt is
trying to solve it.
IFT LAB:
All instrumentation working. Sandra returns home in the next few
days.
MAX PLANK LAB:
Calibration gases expected in the next two weeks and then on-line
measurements will begin mid-late August. Doing just flask samples.
23rd
July 2008
POWER: Some power problems; power cut from yesterday
evening until today at 11:00h. Generator alternator is burned out.
Somebody is coming today to see
it and will take it to town to fix.
INTERNET:
Satellite dish has arrived.Still Doing customs clearance.
YORK LAB: CO,
Ozone, and Noxy instruments running OK;
GC not working
properlly (recovering from a problem)
GC-MS not
working.Preparing to send the MS back to Bristol to be fixed.
MAX-DOAS off because
of mechanical problem with the equipment. Heidelberg people will
be here at the end of August to install new equipment.
Radiometer from
University of Hamburg OK.
Meteorological equipments
running OK.
Aerosol sampling from
U.of Southampton running with just one of the two pumps again.Matt is
trying to solve it.
IFT LAB:
Konrad Muller's team ( Nicole and Sandra) on field campaign.
Nicole will leave tomorrow.Compressor problem solved.
MAX PLANK LAB:
Waiting to start on-line measurements.Doing just flask samples.
15th July 2008
POWER: Stable since last week.
INTERNET:
Satellite dish has arrived. Doing customs clearance.
YORK LAB: CO,
Ozone, and Noxy instruments running OK;
GC not working properly (recovering from a problem)
GC-MS not working.(waiting for smart-card replacement)
MAX-DOAS
off because of mechanical problem with the equipment. Some body from
Udo's team to come on May or June to fix it.
Radiometer from University of Hamburg OK.
Meteorological equipments running OK, (10m) anemometer back in
place since yesterday afternoon but reading 300 degrees more than
the real direction value.
Aerosol
sampling from U.of Southampton running with just one of the two pumps
again.Matt is trying to solve it.
IFT
LAB: Konrad Muller's team (Thomas Mueller, Nicole and
Sandra) on field campaign.Having some problems with the compressor but
may be solved
before the end of this week with
a new one that is coming.
MAX PLANK LAB:
Waiting to start on-line measurements. Doing just flask samples.
|